Blog Grid without Sidebar
Home > Blog Grid without Sidebar
MDC Systems® Presented at ASHRAE, Baltimore Chapter, May 2013
E. Mitchell Swann, Consulting Engineer at MDC Systems®, presented at the ASHRAE Baltimore Chapter Meeting on Thursday, May 2nd. Main Meeting: Design-Build Executing the Project Synopsis: The growing popularity of design-build provides businesses with a unique...
More Than Just Counting Rainy Days: Documenting Weather Delays
by Michelle N. Delehanty, PE, PMP
MDC Systems® Consultant
According to the farmer’s almanac, this upcoming winter is predicted to be more severe than last year, which already seems as if it were one for the record books. For many regions throughout the United States, that means a multitude of storms, extreme cold, and potential closings to schools, offices, and, most problematic, construction sites. These closings of construction projects can lead to schedule delays, change order requests, and ultimately claims. In order for a contractor to justify to the owner that there is indeed a weather-related construction delay, they must demonstrate four specific things: (1) that the delay is within the terms of the contract (2) that the activity delayed had a direct effect on the project end date (was on the critical path), (3) the weather event occurred in excess of the “normal” weather for the season, and (4) there is documentation of which specific activities were delayed on each weather occurrence.
Primavera Scheduling
Robert C. McCue, P.E.
MDC Systems®
Consulting Engineer
Recently, MDC Systems® made the jump from Primavera P3 (version 3.1) to P6. However, the landing was a little rough- initially, erroneous information was received from a Primavera representative and then outside IT consultants had to be brought in to resolve issues with the server installation. If the installation experience is any indicator, it seems likely that P6 will require more IT overhead on an ongoing basis. This is in addition to the learning curve for the new features and capabilities of P6.
Complexity is Often the Culprit in Cost Overruns, Delays
Our long history and experience is that the failure rate for projects in general has remained high. Why haven’t the advances in project management science, computers technology and communications been effectively brought to bear on the engineering and construction business? What about the advertised beneficial impact of 3-D computer-aided design, computerized critical path methods schedules and building information modeling? Are today’s engineers not as good as those who built the mega project of yesteryear like the Panama Canal, Empire State Building or Hoover Dam?
The Standard of Care in a Design Build World
Design-Build Delivery can create new responsibilities for designers where they would not exist in traditional Design-Bid-Builddelivery situations and require new awareness on the part of contractors to the iterative and uncertain world of conceptual design. These new responsibilities require a paradigm shift for both Designers and Contractors as the realities of working together challenge the leadership of the organizations.
For designers the change requires them to abandon their traditionally “client only” focused advice and consent role and adopt a new paradigm of working for, or with, the contractor to deliver an acceptable and profitable product. For the contractor working with and supporting the designer changes the very nature of their previous working relationship. The contractor is now working with and for the people they are all too often at odds with concerning project delivery.
The Surety’s Completion Alternatives for Defaulted Contracts
When faced with a default on their projects, many owners have unrealistic expectations concerning the surety’s obligations under the performance bond. Owners feel frustrated when the surety does not aggressively step in to complete the work. However, under most performance bonds, if the contractor/principal is in default, the surety may discharge its obligations by any one of the following alternatives: (1) finance the contractor/principal to complete the work; (2) obtain a new contractor to complete the work under a direct contract with the owner/obligee; (3) complete the work with a new contractor under a contract with the surety; (4) permit or require the owner/obligee to obtain a new contractor; and…