Providing Expert Solutions For Projects Worldwide

Providing Expert Solutions For Projects Worldwide

Phone: (610) 640-9600

Fax: (484) 301-0969

More Than Just Counting Rainy Days: Documenting Weather Delays

More Than Just Counting Rainy Days: Documenting Weather Delays

by Michelle N. Delehanty, PE, PMP
MDCSystems® Consultant

According to the farmer’s almanac, this upcoming winter is predicted to be more severe than last year, which already seems as if it were one for the record books.  For many regions throughout the United States, that means a multitude of storms, extreme cold, and potential closings to schools, offices, and, most problematic, construction sites.  These closings of construction projects can lead to schedule delays, change order requests, and ultimately claims.  In order for a contractor to justify to the owner that there is indeed a weather-related construction delay, they must demonstrate four specific things:  (1) that the delay is within the terms of the contract (2) that the activity delayed had a direct effect on the project end date (was on the critical path), (3) the weather event occurred in excess of the “normal” weather for the season, and (4) there is documentation of which specific activities were delayed on each weather occurrence.

Contract Weather Delay, Notice, and Recovery

Every construction contract is unique, but most projects will experience a weather event of some sort, and accommodations should be made in the contract to outline just what to do when this occurs.  It is customary for the delay clause in the contract to define two things.  First, exactly what a contractor will get if a weather delay occurs – a time extension only (noncompensable delay), time and monetary damages  (compensable delay), or a combination of the two after a certain number of days.  The compensability of the delays will be laid out in the contract, and will depend on the importance of the completion date, liquidated damages, or other factors.

There will also be a requirement in the contract for the contractor to provide notice of the delay within a certain time period of the delay occurring.  This requirement also varies with the contract; however, it is always in the contractor’s best interest to provide formal notice of a weather delay as soon as there is potential to be one, even if the length of time or cost of the recovery is unknown.  The contractor should also work to provide a recovery schedule to get the project back on track to finish on the agreed upon project end date.

Establishing a solid baseline and knowing the critical path

First, in order for a schedule to show a delay that can be pinpointed to a specific weather event, the baseline schedule has to be established, approved, and updated on a regular basis prior to the event occurring.  In order for the delay to be applicable, it must affect the end date of the project.  Primarily, the delayed activity must be on the critical path of the latest schedule update at the time of the weather event.  For example, if the critical path showed concrete-steel-decking with finish-start relationships, and a storm occurred on a day when the steel was 50% complete causing steel work for two days, then the contractor would get a two day delay (assuming the terms of the contract and abnormal weather clauses allowed it).  Conversely, using that same schedule, if the concrete was 95% complete and delayed for two days because of the storm but steel work was able to continue uninterrupted, there is no delay to the critical path; therefore the contractor shouldn’t get any days.

Additionally, if the delayed activity is not shown to be a critical item at the time the weather event occurs, the contractor must demonstrate that the weather caused a delay long enough to use up all of that activity’s float.  Essentially, the weather event would change the critical path of the schedule to include the delayed activity.  The number of days that can be claimed as weather delays will be those days the activity is delayed less the amount of float the activity had prior to the weather event.  For example, using the critical path discussed above, if concurrent activity landscaping had three days of float but was delayed five while the original critical path activities continued as scheduled, the landscaping would then become critical and add a two day delay to the end date, granting the contractor two days.

Normal Weather

Typically, the contract will aver that weather delays can only be claimed when the weather is in excess of “normal” weather.  For example, if the average rainfall for your region in the month of April is four inches and a delay is claimed during an April that only had two inches of rainfall the entire month, an extension would typically not be granted.  This is because “normal” weather should be accommodated for when the project is baselined.  The same logic can be taken when scheduling certain weather-restricted activities in the winter season.  If the average temperature for the region is always below freezing in January, the durations of concrete related activities should adapt to the amount of work one could reasonably achieve given the low temperatures.

Documentation of the Weather Delay

The golden rule of any change order or claim is to document, document, document.  The only way to make a valid weather delay claim is to record what is happening on the construction site before, during, and after the occurrence of the weather event.  As noted above, it is always best to approach a potential weather event (or any part of a construction project) with an established baseline schedule and progress schedules constantly updated.  Weekly and daily site reports should be kept, noting progress of critical and sub-critical activities on each report.  When the weather event occurs, the daily report should note exactly which activities do not progress and why.  The contractor should notify the owner as soon as they think a delay might be occurring, and the project schedule should be updated for progress to see if changes have been made to either the critical path or the end date.

After the number of delay days has been established based on the field records and it is confirmed that the critical path has been affected, it is the contractor’s obligation to establish that the weather during the delay period was abnormal.  Once all three of these things are met, the contractor can move ahead with a request for additional days.  If a change order is presented to the owner with one of these items missing, the owner should request additional information from the contractor before obliging them with additional time or money.  During the time the delays and contract extensions are being resolved, the contractor should establish a recovery schedule and continue work in order to keep the project from delaying any further.

How Can I Prepare for a Weather Event

With a few months remaining until the uncertainty of the upcoming winter, there is still time for contractors and owners to be proactive. They should make sure that all parties understand the approach to delay claims on weather event, work together to get a baseline schedule approved with a conclusive critical path, and establish procedures on how to approach a weather event by documenting all potential delays.

As an Owner:

  • Review the contract clauses related to weather delay.  If there is no contract clause, establish an approach for delays and potential compensation due to weather.
  • Review the project schedule regarding how many weather days are built in, and require regular updating.
  • Review contractor daily reports concerning weather; confirm the reports are providing enough detail about the ongoing work.
  • Communicate your expectations and reiterate contract requirements with the contractor at meetings.

As a contractor:

  • Review the contract clauses related to weather delay.  If there is no contract clause, seek out the owner’s expectations regarding notice, schedule extension, and compensation.
  • Provide notice to the owner of any potential weather delays.
  • Maintain accurate field records, daily reports, and updated schedules for future reference if a weather delay claim should arise.

If both parties have an understanding of what to expect when a weather event occurs, know which activities are directly affected, and follow the contractual requirements for schedule extension and compensation, dealing with weather delays will be easier and help the rest of the project run smoother.

Related Posts

Once Upon a Time in Construction: When Promises Fall Apart

Once Upon a Time in Construction: When Promises Fall Apart

Our client was distraught and blurted out “ they said it would work” and now we have to demolish it. How did this happen? During the mid-90’s it was feared by the EPA that landfills would soon be at capacity to accept sewage sluge and the EPA had recently banned ocean...

read more
MDCSystems® Taking Off with Commercial Drones

MDCSystems® Taking Off with Commercial Drones

MDCSystems® has recently entered the commercial drone industry with its drone for various inspection and engineering evaluation services. The future for the commercial drone industry looks very bright. In 2015 the U.S. commercial drone market size was an estimated...

read more
Change Orders: Maximizing Benefits for Owners

Change Orders: Maximizing Benefits for Owners

Ronald F. Parisi, P.E.
Former MDC Systems® Project Director

Owners involved in ongoing construction projects are virtually unanimous in recognizing the need to minimize the number and amount of change orders as a way to keep the project costs within budget. In viewing change orders with only this in mind, however, owners may tend to overlook the benefits that the change order process offers to owners. The primary benefits afforded by the change order process are that it allows owners the flexibility to respond quickly, to capitalize upon opportunities and to mitigate problems — both of which frequently arise during the course of construction.

Continue Reading

read more

0 Comments