General Experience

Mr. Sporer has over 30 years of experience on engineering and construction projects within the power, process, industrial, transportation and telecommunications industries. His extensive skills include design, change order review/pricing, cost estimating, CPM scheduling (Primavera P3 & P6), quantity surveying, performance and cost monitoring, cash flow forecasting, contract administration, compensable delay and productivity analysis, and earned value reporting.

Mr. Sporer’s responsibilities typically include forensic review and analysis of activities related to project controls for various projects. Experience acquired at both home office and site locations on projects ranging from $5 million to $4 billion. On multiple occasions he has evaluated and designed the cost and scheduling systems for ongoing projects experiencing budgetary and/or schedule problems.

Consulting Experience

Ethylene Plant, Port Arthur, TX
Plant was rebuilt following a fire and explosion incident. The insurers asserted that the engineering was late and defective and the Construction Management Team allowed the facility to remain out of service due to defective scheduling and expediting of the work. Project schedules were analyzed and an expert report was issued including a full detailed critical path method schedule analysis justifying the work activity durations and the procurement timeframes for pipe spool fabrication, delivery and erection.

Baggage-Handling System, Miami International Airport, Miami, FL
The baggage-handling system installed at the airport resulted in claims due to the overall terminal schedule being delayed greater than three years. Schedules and documents were analyzed to prepare a multi-million dollar claim which resulted in an equitable contract change.

BWI Airport, Baltimore, MD
Provided detailed analysis of the inefficiencies resulting from delays to the structural steel, building enclosure and electrical work which delayed and caused inefficiencies to Siemens’ installation and testing work for the baggage handling system. Project resulted with a favorable contract change.

Automated Highway Control System, Boston MA. (Big Dig)
On behalf of Honeywell, investigated and analyzed the cost and schedule overruns for the computer monitoring and control system for highway complex. In addition to normal construction issues, it was determined that the most significant cost and schedule driver for this project was the poorly defined architecture for the central computer system, a failure to understand the significant technology changes that had occurred while the project was underway and the rising expectations of the MTA, for state-of-the-art systems which could not function in the obsolete base design configuration provided by MTA.

Tyson Event Center, Sioux City, IA
The structural steel erection was delayed due to late deliveries and misfabrication. Schedules and cost reports were analyzed to develop a successful claim resolution before litigation proceeded.

Churchill Downs Clubhouse Renovations, Louisville, KY
Project experienced cost overruns due to inadequate site conditions and insufficient bid drawing details.

Phillies Citizens Bank Ball Park, Philadelphia, PA
Served as on-site scheduling consultant for a well-respected electrical contractor. Developed scheduling fragments to complete additional work scope items.

School Construction Projects, Various Cities and States
Incorporated client-approved change orders into the project schedule to graphically display schedule impact.

Milford Power Plant, Milford, CT
Analyzed change orders and project schedules to determine responsibility of a two-year delay in the substantial completion date of a new 500Mw gas-fired combined cycle power plant. Wrote bi-weekly site observation construction reports used to develop As-Built schedules and substantiate the ongoing progress for our client.

Detroit Metro Airport, Steel/Metal Deck Erection, MI
Analyzed change orders and schedules and reviewed the project cost reporting system to determine the cumulative financial impact caused by scope changes after shop fabrication of steel was begun. Although these design changes did not increase the scope, an analysis was performed that quantified the impact of out of sequence work.

Project Experience

Chemical Process Facility, Aberdeen, MD
Served as Project Controls Manager – Reviewed and independently priced piping, electrical, and equipment change orders for a $700 million government-owned chemical process facility. Developed cost options to choose the most economical method of incorporating design changes. Used System Dynamics, a computer-modeling program simulation to enhance construction claims.

Telecommunication Projects, Eastern U.S
Served as Assistant Project Manager – Responsible for developing cost and schedule control systems, work breakdown structures, contract administration, monthly project reports and resource allocation on a $400 million telecommunications project. Developed earned value reports after reviewing the project schedule and other budget reports.

PSE&G Rehabilitation Project, Burlington, NJ
Instituted project control methods to reduce a potential overrun situation. Methods included budget allocation at sub work package levels, accelerating the project schedule by 25%, liquidated damages on key delivery items and daily progress and site/construction coordination meetings.

Northeast Inlet Infrastructure Project, Atlantic City, NJ
Served as Project Controls Manager – Responsible for developing all cost and schedule control systems, work breakdown structures, contract administration, client billing and resource allocation.

Nine Mile Point 2 Nuclear Power Plant, Oswego, NY
Served as Project Cost Engineer – Responsible for the project control part of the discovery process where client claimed that schedule delays caused project overruns. Coordinated cost functions for developing, maintaining and analyzing estimates, forecasts, and change control procedures for a $4.1 billion nuclear power plant. Supervised 20 project cost, estimating, and change control personnel. Used System Dynamics, a computer-modeling program simulation to enhance construction claims.

Oyster Creek Generating Station, Lacey Township, NJ
Served as Project Cost Engineer – Developed detailed preliminary and budgetary estimates in a format consistent with the construction schedule and with the client’s accounting system. This allowed the client to incorporate the estimate directly into its mainframe cost tracking system. The scope of work consisted of designing a structure and associated facilities to accommodate two diesel generators.

Coal/Oil Fired Cogeneration Plant, Deepwater Station, NJ
Served as Project Cost Engineer – Developed estimates, change controls systems, cash flow forecasts, schedule and earned value reports. Allocated specific cost sharing between users of the steam and electric products.

BL England Coal Fired Generating Station, Cape May County, NJ
Served as HeadQuarters and Site Project Cost Engineer – Developed numerous initial feasibility studies to determine the most economical methods to make government mandated environmental changes. Developed all estimates and project control systems and developed the construction cost/schedule reports for weekly project monitoring.

Power Production, U.S.
Served as Staff Estimator – Developed and updated numerous project capital cost estimates. Disciplined estimated included mechanical, civil/structural, electrical, and geotechnical. Quantity takeoffs were performed on drawings of all disciplines.

Presentations

Facilities Delivery: Managing Fast Track Projects in a Regulated Environment, Critical Path Scheduling, ISPE Winter Conference, Tampa, FL

Education

  • Pennsylvania State University, A.S., Electrical Engineering, 1974

Professional Affiliations

  • Association for the Advancement of Cost Engineering: Member
  • Association for International Arbitration (AIA): Professional Member

 

MDCSystems®: Your Trusted Partner for Project Issue Resolution and Expert Testimony 

MDCSystems® determines and verifies facts to facilitate problem resolution during the life of a troubled project. We review and organize all available pertinent data to document technical issues, schedule performance and project management, and assist clients with document discovery, document management and strategy development for all elements of the litigation process. MDCSystems® licensed senior professionals prepare expert reports and will testify as expert witnesses in depositions, arbitrations and trials with state-of-the-art demonstrative evidence.