Providing Expert Solutions For Projects Worldwide

Providing Expert Solutions For Projects Worldwide

Phone: (610) 640-9600

Fax: (484) 301-0969

Blog Fullwidth without Sidebar

Home > Blog Fullwidth without Sidebar

The Surety’s Completion Alternatives for Defaulted Contracts

The Surety’s Completion Alternatives for Defaulted Contracts

When faced with a default on their projects, many owners have unrealistic expectations concerning the surety’s obligations under the performance bond. Owners feel frustrated when the surety does not aggressively step in to complete the work. However, under most performance bonds, if the contractor/principal is in default, the surety may discharge its obligations by any one of the following alternatives: (1) finance the contractor/principal to complete the work; (2) obtain a new contractor to complete the work under a direct contract with the owner/obligee; (3) complete the work with a new contractor under a contract with the surety; (4) permit or require the owner/obligee to obtain a new contractor; and…

Continue Reading

read more
Project Risk Reduction

Project Risk Reduction

Using Project Management Modeling Tools to Quantify, Analyze and Reduce Exposure to Risk

Some project histories are very complex and traditional schedule and damage analysis methods are not able to quantify the impacts of events that have occurred over the life of the project. In these situations MDC&Reg has relied upon more sophisticated mathematical and system based models to attribute impacts to particular events. The usual methods of determining and reducing risk on construction projects include schedule forecast, cost forecasts and change review analysis performed by the project team. However, sometimes these techniques do not allow for an overview that properly adds the effects of many individual events. On these occasions the project team needs more powerful and sophisticated tools that can include multiple project factors including resource availability, site conditions, environmental factors and productivity levels for both planned and actual conditions on the project to date, all factors that cannot be completely comprehended by the project manager without the aid of analysis.

Continue Reading

read more