Where is the critical path? This is one of the questions most often asked concerning schedule analysis. For some types of projects it is easy to anticipate where the critical path should be; for instance in high-rise building construction, the critical path is most likely to be: excavation, foundation, structure, weather enclosure (building envelope), MEP, finish activities.