Oman Combined Cycle Power Plant

Client Name: Stone & Webster Engineering, Inc.

MDC® was asked to investigate and analyze a contract with Petroleum Development Oman (PDO) for the detailed engineering and construction of a gas-fired turbine electric generating plant located in Oman at Saih Rawl. The power plant was to supply electrical power to the national grid and to the adjacent gas processing plant. A waste heat recovery unit in the power plant was to provide process heat to an adjacent gas plant being constructed by others.

Singapore Pharmaceutical Project

Client Name: Schering-Plough

Singapore Pharmaceutical Project – MDC® was asked to investigate and analyze the delay and cost overrun experienced on this bulk pharmaceutical manufacturing project in Singapore. MDC® conducted extensive site visits and personnel interviews to determine the major problems experienced in the construction of the facility.

Delaware Manufacturing Plant

Client Name: Durr Automation

MDC® was retained by a Prime Contractor against General Motors on a $200MM(+) expansion project. MDC® assisted the prime contractor in preparing its statement of claim as well as defending itself against claims brought by their subcontractor. MDC®’s analysis work involved verification of labor and equipment costs and attribution of costs to various conditions including the impact of design changes, local plant requested changes and the unforeseen discovery of hazardous materials and its removal which disrupted the planned work flow.

Indiana Manufacturing Plant Project

Client Name: Sun Oil Company

MDC® was retained to review engineering, procurement and construction issues concerning the development of a coke (coal) manufacturing plant in Indiana. Our client’s damages stemmed from the differential movement of the sub-grade beneath the coke oven battery foundations and the failure of the coke ovens’ exhaust gas system to maintain adequate negative process pressures.

Airbag Manufacturing Facility Project

Client Name: Talley Industries

MDC® was retained by an airbag manufacturing company to consult and provide expert witness services for the evaluation of a $40 million claim against our client for defective design and construction of an airbag manufacturing plant. After the plant was sold to a third party, our client constructed additions and modifications to the plant, increasing production capacity dramatically. Part of the plant in which the explosive pellets are manufactured was involved in a catastrophic failure.

FIT

Client Name: Dean Mead

MDC® was retained by a university in Florida to develop an analysis of the events and issues that arose during the construction of the university buildings. MDC® performed a comprehensive schedule analysis of the causes and liability for delay during the project. This analysis required verification of the contractor’s initial schedule and the subsequent updates to determine their accuracy and reliability as a basis for analysis.

School District Project

Client Name: Catasauqua Area School District

MDC® was retained by a general contractor and a Pennsylvania school district, to analyze change orders submitted by the general contractor to the school district for excessive costs associated with the removal of rock found after excavation of the proposed site for a new high school. The new high school was first estimated with a total budget amount of $20,995,100 with actual construction costs exceeding $25,356,024. MDC® determined that due to poor planning and testing by the Architect the school district was entitled to recover the excessive costs for rock removal from the Architect.

Suburban School District Energy Project

MDC® was retained by a school district in Pennsylvania to investigate, analyze and recommend corrective action for the high school HVAC System due to high operating costs and unacceptable temperature conditions in various rooms of the school. The high school had been recently constructed and incorporated a geothermal field for heating and cooling uses.

University Library Project

MDC® was retained by a university in New Jersey to determine if problems existed with the building design of the university library. The university had experienced problems maintaining the interior environment of the library within normally accepted ranges for this type of facility. The university suspected that the problems were the result of errors in the design of the building and its mechanical system.